KEY SPECIFICATIONS
- Usage: Commercial Store
- Size: 5,189 sq ft
- Start Date: June 2023
- End Date: December 2023
At ODH Building Services, we bring extensive design expertise and experience in plumbing, heating, and ventilation solutions across a wide range of sectors.
Our end-to-end, in-house BIM (Building Information
Modelling) service guides clients through every stage
of the project—from pre-construction to the final ‘AsBuilt’ handover
By leveraging cutting-edge BIM technologies and clash
detection software, we ensure that our models are:
This approach not only streamlines the construction
process but also enhances efficiency and cost effectiveness throughout the project lifecycle.
Commercial Store
Private Hospital
Public / Airport
60 GROVE END ROAD
NW8 9NH
ODH were appointed to design, supply, and install new mechanical pipework and a full airside package, including basement and rooftop AHUs, supply and extract ductwork, riser pipework modules, and fully equipped plant areas housing boilers and calorifiers.
The installation also included radiant ceiling panels and LST radiators throughout the facility.
Our scope encompassed full testing, commissioning, and witnessing of all systems.
The project delivered cutting-edge orthopaedic and general operating theatres on the first floor, complemented by a suite of private patient rooms across the remaining levels.
Key Challenges and Our Approach
Live Hospital Environment: Operating within and adjacent to an active hospital required meticulous coordination to ensure patient care remained uninterrupted.
Tight Programme & Long Lead Items: The programme was demanding, with high-specification equipment requiring long lead times, necessitating precise scheduling and logistics.
Complex Design: The technical complexity of the design demanded a high level of detail and collaboration from the outset.
Our Solution We successfully navigated these challenges through thorough planning, early-stage design development, and consistent communication with our client, supply chain, and stakeholders. Our collaborative approach and attention to detail ensured that we delivered a high-quality project safely and efficiently, within a challenging live hospital environment.
The project was delivered on time and within budget, exceeding expectations despite the complex working environment. It stands out as a benchmark achievement, and the client was extremely pleased with the quality of the finished product.
HARTMANN ROAD
E16 2PX
ODH were responsible for upgrades to customer facilities at London City Airport.
Our scope included:
This was a particularly challenging project due to the nature of the site, being a busy operational airport.
Close attention was paid to all operatives working in and around the site, security clearance, and strategically coordinated material deliveries.
Through careful planning, highly detailed communication, and regular site visits, we were able to manage the project effectively.
The project was delivered on time and within budget, fully meeting the client’s requirements and expectations.